When do construction phase services under agency CM typically begin?

Prepare for the Project Delivery Test with flashcards and interactive questions. Enhance your understanding and get exam-ready with our comprehensive resources. Master project delivery concepts effectively!

Construction phase services under agency construction management (CM) typically begin once the pre-construction phase is completed. This phase encompasses all the activities that take place before actual construction starts, including project planning, design finalization, budgeting, scheduling, and pre-bid procedures.

Once the pre-construction phase concludes, the agency CM can transition into providing construction phase services effectively. These services include oversight of the construction process, ensuring that project timelines and budgets are adhered to, and facilitating communication among all parties involved. Thus, knowing when the pre-construction phase is completed is crucial for the agency CM to assume its role during construction, where their focus shifts to managing the execution of the project in alignment with the established plans and specifications.

Completion of the pre-construction phase marks the readiness to move into the actual construction work, allowing the agency CM to begin their oversight and management tasks, ensuring a successful project delivery.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy